Task Assignment in Project Server 2010

There has been some scenario relating to Task status updates going to the EPM Administrator who create the Project and assigned a task to one Team member. However, during the course of time the Project ownership was transfered to a real Project Manager. Now after the ownership transfer occured the Team member updated his task and it directed to the Original Project owner (EPM administrator) who rejected the task.

Now This was a issue as it was not going to the Newly assigned Project Manager.

The resolution to this issue is simple:

Ensure the Project Manager opens the newly assigned project in Project Professional 2010 and Publishes it from his/her account; This will seal the ownership of the Project to newly assigned project manager and all previous pending task updates will now flow to this Project Manager.

Kinly let me know if you have any further questions on this item....


I hope this helps and assists you in your EPM / PPM Endeavor. Best Regards,Gokul Rajan